Project Schedule

Highlight Construction Loft Conversion Typical Works Schedule

Activity Timescales
  Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7
Pre-Start Set Up              
Agree scope of job              
Agree timings and access              
Produce drawings (if required)              
Assist with planning application              
Main Build              
Erect scaffolding              
Install steel supports              
Install floor              
Build dormer and roof              
Install Stairs              
Services              
Fit electrics & Plumbing              
Install windows              
Plastering              
2nd fix - carpentry, plumbing, electrics              
Final Fix              
Snagging list              
Decorating (if required)              
Client Reviews              

Newsflash

We can also offer a partial (skeleton) loft conversion with a dormer, stairs and floor installation for the competent diy enthusiast to complete him/herself. This way it will reduce your costs, you feel involved with the project and that you are part of the process that gives you job satisfaction.

Testimonials

"Everybody was so helpful and polite, their work ethic was excellent always on time and always left all areas clean and tidy at the end of the day. Very pleased with the final finish, no hassle at all, would confidentially recommend to anyone" Paul and Melanie, Barnes